Dense Media Cyclone Optimization Quarterly Technical Progress Report: July-September 2003 (open access)

Dense Media Cyclone Optimization Quarterly Technical Progress Report: July-September 2003

All technical project activities have been successfully completed. This effort included (1) completion of field testing using density tracers, (2) development of a spreadsheet based HMC simulation program, and (3) preparation of a menu-driven expert system for HMC trouble-shooting. The final project report is now being prepared for submission to DOE comment and review. The submission has been delayed due to difficulties in compiling the large base of technical information generated by the project. Technical personnel are now working to complete this report. Effort is being underway to finalize the financial documents necessary to demonstrate that the cost-sharing requirements for the project have been met.
Date: September 9, 2003
Creator: Luttrell, Gerald H.
System: The UNT Digital Library
Dense Media Cyclone Optimization Quarterly Technical Progress Report: October-December 2003 (open access)

Dense Media Cyclone Optimization Quarterly Technical Progress Report: October-December 2003

All technical project activities have been successfully completed. This effort included (1) completion of field testing using density tracers, (2) development of a spreadsheet based HMC simulation program, and (3) preparation of a menu-driven expert system for HMC trouble-shooting. The final project report is now being prepared for submission to DOE comment and review. The submission has been delayed due to difficulties in compiling the large base of technical information generated by the project. Technical personnel are now working to complete this report. Effort is being underway to finalize the financial documents necessary to demonstrate that the cost-sharing requirements for the project have been met.
Date: January 15, 2003
Creator: Luttrell, Gerald H.
System: The UNT Digital Library
Dense Media Cyclone Optimization Quarterly Technical Progress Report: April-June 2002 (open access)

Dense Media Cyclone Optimization Quarterly Technical Progress Report: April-June 2002

All project activities are now winding down. Follow-up tracer tests were conducted at several of the industrial test sites and analysis of the experimental data is currently underway. All required field work was completed during this quarter. In addition, the heavy medium cyclone simulation and expert system programs are nearly completed and user manuals are being prepared. Administrative activities (e.g., project documents, cost-sharing accounts, etc.) are being reviewed and prepared for final submission to DOE. All project reporting requirements are up to date. All financial expenditures are within approved limits.
Date: September 14, 2002
Creator: Luttrell, Gerald H.
System: The UNT Digital Library