FY94 and FY95 thermal stabilization campaign report (open access)

FY94 and FY95 thermal stabilization campaign report

The report provides a synopsis of the FY94/95 Thermal Stabilization Campaign. The FY94 Thermal Stabilization Campaign ran from November 1, 1994 to June 13, 1995 and stabilized 236 items (22 kg) of reactive plutonium bearing material. A total of 49 cans of stabilized material was moved to the vaults for interim storage. While the initial downtime was high, with an Operating Efficiency (OE) of 27% over the first 3 months, the OE improved to 78% during the last 5 months for an overall DE of 58%. The campaign was completed 85 days ahead of schedule thus exceeding the ``Excellent``date for the Performance Base Incentive (PBI) for this campaign by 25 business days.
Date: January 10, 1996
Creator: Lewis, W.S.
System: The UNT Digital Library