Annual Hanford Seismic Report for Fiscal Year 2007 (open access)

Annual Hanford Seismic Report for Fiscal Year 2007

This annual report documents the locations, magnitudes, and geologic interpretations of earthquakes recorded for the Hanford monitoring region of south-central Washington in fiscal year 2007 (October 2006 through September 2007). The report provides summaries of seismic events recorded during the first three quarters of fiscal year 2007 and contains a more comprehensive discussion of seismic events for the fourth quarter of the fiscal year.
Date: December 27, 2007
Creator: Rohay, Alan C.; Sweeney, Mark D.; Hartshorn, Donald C.; Clayton, Ray E. & Devary, Joseph L.
System: The UNT Digital Library
FY07 Final Report for Calibration Systems (open access)

FY07 Final Report for Calibration Systems

Remote infrared (IR) sensing provides a valuable method for detection and identification of materials associated with nuclear proliferation. Current challenges for remote sensors include minimizing the size, mass, and power requirements for cheaper, smaller, and more deployable instruments without affecting the measurement performance. One area that is often overlooked is sensor calibration design that is optimized to minimize the cost, size, weight, and power of the payload. Yet, an on-board calibration system is essential to account for changes in the detector response once the instrument has been removed from the laboratory. The Calibration Systems project at Pacific Northwest National Laboratory (PNNL) is aimed towards developing and demonstrating compact quantum cascade (QC) laser-based calibration systems for infrared sensor systems in order to provide both a spectral and radiometric calibration while minimizing the impact on the instrument payload. In FY05, PNNL demonstrated a multi-level radiance scheme that provides six radiance levels for an enhanced linearity check compared to the currently accepted two-point scheme. PNNL began testing the repeatability of this scheme using a cryogenically cooled, single-mode quantum cascade laser (QCL). A cyclic variation in the power was observed that was attributed to the thermal cycling of the laser's dewar. In FY06, PNNL …
Date: December 1, 2007
Creator: Myers, Tanya L.; Broocks, Bryan T.; Cannon, Bret D. & Ho, Nicolas
System: The UNT Digital Library
HYBRID SULFUR ELECTROLYZER DEVELOPMENT, NHI WORK PACKAGE N-SR07TC0301, FY07 FIRST QUARTER REPORT (open access)

HYBRID SULFUR ELECTROLYZER DEVELOPMENT, NHI WORK PACKAGE N-SR07TC0301, FY07 FIRST QUARTER REPORT

The proof of concept of SO2 electrolysis for the hybrid sulfur (HyS) process is the second priority research target of the DOE Nuclear Hydrogen Initiative's thermochemical program for FY07. The proof of concept of the liquid-phase option must be demonstrated at the single cell level for an extended run times (>100 hours). The rate of development of HyS will depend on the identification of a promising membrane or an alternative means for controlling sulfur formation. Once successful long-duration operation has been demonstrated, SRNL will develop a multi-cell stack that can be connected to the H2SO4 decomposer being developed by SNL for the S-I ILS for a Hybrid Sulfur Integrated Laboratory-Scale Experiment during FY 2008. During the first quarter of FY07, SRNL continued the component development and membrane development activities with the goal of identifying and characterizing improved electrodes, electrocatalysts, membranes and MEA configurations which could then be tested at larger scale in the SDE test facility. A modified glass cell was fabricated to allow measurements of sulfur dioxide (SO2) transport across membrane samples at elevated temperatures (up to 70 C). This testing also includes evaluating SO2 transport in different sulfuric acid concentrations (30-70 wt%). A new potentiostat/frequency analyzer was installed …
Date: December 20, 2006
Creator: Summers, W
System: The UNT Digital Library
FY07 I/O Integration Blueprint (open access)

FY07 I/O Integration Blueprint

This document provides an understanding of the near and long term computing and I/O resources in the Secure Computing Facility (SCF) and Open Computing Facility (OCF). Requirements for data flows, storage capacities and transfer rates are determined. Recommendations are made for architectures, timeframes for major deliverables, and procurements for the next fiscal year.
Date: December 28, 2006
Creator: Wiltzius, D P & Gary, M R
System: The UNT Digital Library
Technical Issues Map for the NHI System Interface and Support Systems Area: 1st Quarter FY 07 (open access)

Technical Issues Map for the NHI System Interface and Support Systems Area: 1st Quarter FY 07

This document provides a mapping of technical issues associated with development of the Next Generation Nuclear Plant (NGNP) intermediate heat transport loop and nuclear hydrogen plant support systems to the work that has been accomplished or is currently underway. The technical issues are ranked according to priority and by assumed resolution dates. Due to funding limitations, not all high-priority technical issues are under study at the present time, and more resources will need to be dedicated to tackling such issues in the future. This technical issues map is useful for understanding the relative importance of various technical challenges and will be used as a planning tool for future work package planning.
Date: December 1, 2006
Creator: Sherman, Steven R.
System: The UNT Digital Library