3 Matching Results
Results open in a new window/tab.
Results:
1 - 3 of
3
Production Test No. 105-522-E, Examination of pile process tubes
The objective of the production test described in this report is to provide the authority and mechanism to remove process tubes from the piles for inspection. The test is intended to provide a more positive tube inspection program than was previously provided under production test number 105-9-P, ``Corrosion of Slugs and Tubes``, document number 7-3928.
Date:
May 25, 1953
Creator:
Falkoski, R. E.
System:
The UNT Digital Library
INVESTIGATIONS FOR THE PRODUCTION OF THORIUM METAL. Technical Progress Report for Fourth Quarter, February 1 to April 30, 1953
None
Date:
May 25, 1953
Creator:
Sibert, M.E.
System:
The UNT Digital Library
Production test number 105-519-E -- Raising permissible outlet water temperatures of selected tubes at C Pile
This report describes the objective of this production test which is to simulate with a few tubes operation of the old piles with small water annulus at power levels in the range of 800--900 MW.
Date:
May 25, 1953
Creator:
Goldsmith, S.
System:
The UNT Digital Library