Scavenging of stored TBP waste (open access)

Scavenging of stored TBP waste

The reactivation of B-Plant and the continued operation of T-Plant under the 4X Program have led to the problem of obtaining additional underground tankage in both 200 East Area and 200 West Area for the storage of B-Plant metal waste, second cycle waste sludge, 224-B Building waste sludge, B and T-Plant first cycle waste scavenged sludge, and perhaps additional TBP concentrated wastes. As a result of this problem, a study has been made to determine the engineering feasibility of using a scavenging type process, similar to that used in the TBP Plant, for recovering the storage space in tanks currently filled with TBP wastes. The results of this study are reported herein. The purpose of this document is to present the scope, justification, and engineering feasibility of a nickel ferrocyanide scavenging system for stored TBP wastes.
Date: February 28, 1955
Creator: Poucher, F. W. & Ingalls, W. P.
System: The UNT Digital Library
Addendum to Production Test 221-T-19 reduction of time cycle in dissolver section (open access)

Addendum to Production Test 221-T-19 reduction of time cycle in dissolver section

None
Date: February 9, 1955
Creator: Schmidt, W. C.
System: The UNT Digital Library
Steam loss at 190-B, D, DR, F, and H Buildings (open access)

Steam loss at 190-B, D, DR, F, and H Buildings

None
Date: February 25, 1955
Creator: Stainken, F. A. R.
System: The UNT Digital Library
A study to determine the economical tank size for radioactive waste disposal (open access)

A study to determine the economical tank size for radioactive waste disposal

Purpose of this report is to determine optimum tank size from evaluating the quantities of principal construction materials with prevailing unit costs for various tank sizes. The materials were concrete in-place, reinforcing steel in-place, wood framework, 3/8 in. C steel plate liner in-place, earthwork excavation and backfill (engineering, overhead, piping, condenser, vapor manifold costs not included). Costs of optimum tank are distributed as follows: dome 25%, walls 28%, foundation 6%, floor 2%, steel liner 20%, earthwork 19%. For a given tank capacity, there is a definite optimum tank size; as the capacity increases, the diameter increases, and the height increases but at a lesser rate. Each diameter has an optimum height, which is that height at which unit cost of storage space is minimum for a given tank diameter. Optimum unit cost is $0.136/gallons for diameters 75--130 ft; for diameters<75 ft, the optimum unit increases. Tank forms 241-S, 241-SX, and 241-A were used in this study; storage cost of the analyzed tank was $0.121 compared to $0.136/gallon for 241-SX and 241-A, and $0.152/gallon for 241-S. Assumed unit costs for concrete and steel plate tank liner were 10% less than those of 241-SX and 241-A, causing the lower unit costs. Tanks …
Date: February 11, 1955
Creator: Stivers, H. W.
System: The UNT Digital Library
Interim report, production test-105-522-E, examination of pile process tube removed from 100-B and 100-H Piles (open access)

Interim report, production test-105-522-E, examination of pile process tube removed from 100-B and 100-H Piles

This report covers the examination of nine process tubes, five tubes from B Pile and four from H Pile. Four of the tubes from B File were removed because they were leaking and the fifth was removed because it contained a stuck ruptured slug. Tube 2681-H was removed for graphite mining, tube 2852-H was removed under PT 313-105-14M ``In-Pile Evaluation of 63-S Aluminum Process Tubes,`` and two tubes were removed from channel 0961-H under PT 105-506-E, ``Recirculation of Pile Cooling Water.`` Visual inspection was made of the inside and outside surfaces of the tubes before and after cleaning with cold 10 per cent nitric acid. Samples varying from one to four inches in length were taken from each section and transferred to the 108-B Metallurgical Laboratory for close examination to determine depth of pitting, 72-S cladding thickness, and wall thickness. These determinations were made at specific points in each section on what appeared to be the area of severest attack. It is indicated on six of the tubes where the sample was taken on the circumference of the tube.
Date: February 10, 1955
Creator: Strege, D. E.
System: The UNT Digital Library
Investigation of KW reactor incident (open access)

Investigation of KW reactor incident

The new KW reactor was placed in operation on January 4, 1955, and had been running at relatively low power levels for only 17 hours when it was shut down because of a process tube water leak which appeared to be associated with a slug rupture. After several days of unrewarding effort to remove the slugs and tube by customary methods, it developed that considerable melting of the tube and slugs had taken place. It was then evident that removal of the stuck mass and repairs to the damaged tube channel would require unusual measures that were certain to extend the reactor outage for several weeks. This report documents the work and findings of the Committee which investigated the KW reactor incident. Its content represents unanimous agreement among the three Committee members.
Date: February 11, 1955
Creator: Sturges, D. G.; Hauff, T. W. & Greager, O. H.
System: The UNT Digital Library
Precipitation of Uranium Ammonium Fluoride From UNH Solutions as an Intermediate in the Preparation of Uranium Tetrafluoride (open access)
Rotation of Polarization Vector and Depolarization in P-PScattering (open access)

Rotation of Polarization Vector and Depolarization in P-PScattering

None
Date: February 14, 1955
Creator: Ypsilantis, T.; Wiegand, C.; Tripp, R.; Segre, E. & Chamberlain, O.
System: The UNT Digital Library
Construction status report - 100-C for week ending - February 6, 1955 (open access)

Construction status report - 100-C for week ending - February 6, 1955

None
Date: February 7, 1955
Creator: unknown
System: The UNT Digital Library
Hanford Atomic Products Operation monthly report, January 1955 (open access)

Hanford Atomic Products Operation monthly report, January 1955

This document presents a summary of work and progress at the Hanford Engineer Works for January 1955. The report is divided into sections by department. A plant wide general summary is included at the beginning of the report, after which the departmental summaries begin. The Manufacturing Department reports plant statistics, and summaries for the Metal Preparation, Reactor and Separation sections. The Engineering Department`s section summarizes work for the Technical Design, and Project Sections. Costs for the various departments are presented in the Financial department`s summary. The Medical, Radiological Sciences, Utilities and General Services, Employee and Public Relations, and Community Real Estate and Services departments have sections presenting their monthly statistics, work, progress, and summaries.
Date: February 21, 1955
Creator: unknown
System: The UNT Digital Library
Massachussetts Institute of Technology progress report (open access)

Massachussetts Institute of Technology progress report

This is the thirty-sixth progress report of the Laboratory for Nuclear Science at the Massachusetts Institute of Technology. Progress during the period of November 30, 1954 through February 28, 1955 is reported.
Date: February 28, 1955
Creator: unknown
System: The UNT Digital Library
Medical and Health Physics Quarterly Report for October, November, December 1954 (open access)

Medical and Health Physics Quarterly Report for October, November, December 1954

None
Date: February 28, 1955
Creator: unknown
System: The UNT Digital Library
Medical and Health Physics Quarterly Report October, November,December 1954 (open access)

Medical and Health Physics Quarterly Report October, November,December 1954

None
Date: February 28, 1955
Creator: unknown
System: The UNT Digital Library
QUARTERLY SUMMARY RESEARCH REPORT IN METALLURGY FOR JULY, AUGUST, AND SEPTEMBER 1954 (open access)

QUARTERLY SUMMARY RESEARCH REPORT IN METALLURGY FOR JULY, AUGUST, AND SEPTEMBER 1954

None
Date: February 17, 1955
Creator: unknown
System: The UNT Digital Library
Redox Plant shutdown, January 8, 1955--February 2, 1955 (open access)

Redox Plant shutdown, January 8, 1955--February 2, 1955

This report summarizes work completed during the Redox Plant shutdown in January 1955. An analysis of major difficulties encountered, improvements made during the shutdown, and building design deficiencies brought to light by the shutdown are discussed. (JL)
Date: February 15, 1955
Creator: unknown
System: The UNT Digital Library
Savannah River Plant heavy water: 400 Area. Monthly report, January 1955 (open access)

Savannah River Plant heavy water: 400 Area. Monthly report, January 1955

This report presents the details of the operations of the Savannah River Plant manufacturing division during the month of January 1955.
Date: February 15, 1955
Creator: unknown
System: The UNT Digital Library
Weekly report - 100 areas - February 3, 1955 (open access)

Weekly report - 100 areas - February 3, 1955

None
Date: February 3, 1955
Creator: unknown
System: The UNT Digital Library
Weekly report - 100 areas - February 10, 1955 (open access)

Weekly report - 100 areas - February 10, 1955

None
Date: February 10, 1955
Creator: unknown
System: The UNT Digital Library