GT-MHR Commercialization Study Technical Progress and Cost Management Report: May 2003 (open access)

GT-MHR Commercialization Study Technical Progress and Cost Management Report: May 2003

A271 GT-MHR COMMERCIALZATION STUDY TECHNICAL PROGRESS AND COST MANAGEMENT REPORT FOR THE PERIOD MAY 1 THROUGH MAY 31, 2003. Petten advised GA the start of the HFR-EU2 irradiation is being delayed until late July 2004. HFR-EU1 (pebble fuel) is also delayed until February/March 2004. The reason for the delays was implementation of new financial regulations at Petten that delayed the contracts for capsule fabrication. Review of the MHR-2 Fuel Product Specification was completed. Revision of the specification to incorporate the review results is in progress. Detailed test matrices have been drafted for capsule irradiation tests and for post-irradiation heating tests proposed for development and qualification of advanced coated-particle fuels capable of meeting anticipated VHTR fuel performance requirements.
Date: May 1, 2003
Creator: Shenoy, A. S.