Resource Type

Analysis of Coaxial Two-Terminal Conical Capacitor (open access)

Analysis of Coaxial Two-Terminal Conical Capacitor

From Abstract: "The electric field is plotted and its construction steps for axial symmetry are given."
Date: April 6, 1962
Creator: Selby, M. C.
System: The UNT Digital Library
Bibliography of Temperature Measurement: January 1953 to June 1960 (open access)

Bibliography of Temperature Measurement: January 1953 to June 1960

Report presenting more than 500 references to the field of temperature measurement. These references were collected from two general sources: Scientific and technical literature and government reports. The period covered is from 1953 to June 1960, with some from earlier dates. References are divided into a number of categories based on the type of instrument used. Some references to calibration of instruments and to scientific theories upon which temperature measurement is based are also presented.
Date: April 6, 1961
Creator: Halpern, Carl & Moffat, Robert J.
System: The UNT Digital Library
Mathematics Panel: Annual Progress Report for Period Ending December 31, 1960 (open access)

Mathematics Panel: Annual Progress Report for Period Ending December 31, 1960

Programming research in the construction of a translator to Oracle language from ALGOL.
Date: April 6, 1961
Creator: unknown
System: The UNT Digital Library
Gas-Cooled Reactor Project Quarterly Progress Report: December 1961 (open access)

Gas-Cooled Reactor Project Quarterly Progress Report: December 1961

Report documenting ongoing research and developments at the Oak Ridge National Laboratory's Gas-Cooled Reactor Project.
Date: April 6, 1962
Creator: Oak Ridge National Laboratory
System: The UNT Digital Library
SM-2 Final Design Progress Review Report: December 16, 1959 to March 1, 1960 (open access)

SM-2 Final Design Progress Review Report: December 16, 1959 to March 1, 1960

From introduction: "The contract covers final design of the SM-2 Nuclear Power (PWR) Steam Electric Station, described in the preliminary design report, APAE 40, Volumes I and II."
Date: April 6, 1960
Creator: Knighton, G. W.
System: The UNT Digital Library
Hanford Isotopes Production Plant (open access)

Hanford Isotopes Production Plant

This report provides an estimation of cost and manpower for construction of the Hanford Isotopes Production Plant.
Date: April 6, 1964
Creator: Smith, C.W.
System: The UNT Digital Library
Report on 8-inch isostatic press explosion at Site 300 (open access)

Report on 8-inch isostatic press explosion at Site 300

On 3 March 1960 at 11:30 a.m. a detonation occurred in the 8-inch isostatic press. The press and building were completely destroyed. Operating personnel were protected and no injuries resulted. Adjacent facilities were not affected. The press was housed in a temporary facility located in the southwest portion of Section 26, Site 300. The facility was situated approximately 1000 feet west of the main site road, and 1400 feet north of the county road. The press building was of frangible wood construction and was surrounded by an earth barricade. A remote control building, provided with overhead protection, a mechanical equipment room, and a transportainer magazine were located outside the barricaded press building.
Date: April 6, 1960
Creator: unknown
System: The UNT Digital Library
PM-1 Nuclear Power Plant Program: 8th Quarterly Progress Report, December 1, 1960 to February 28, 1961 (open access)

PM-1 Nuclear Power Plant Program: 8th Quarterly Progress Report, December 1, 1960 to February 28, 1961

From abstract: The objective is the design, development, fabrication, installation and initial testing and operation of a prepackaged, air-transportable, pressurized water reactor nuclear power plant, the PM-1.
Date: April 6, 1961
Creator: Sieg, J. S.
System: The UNT Digital Library
630A Maritime Nuclear Steam Generator Scoping Study (open access)

630A Maritime Nuclear Steam Generator Scoping Study

From foreword: This report presents the results of a study of a nuclear steam generator which uses reactor technology during the aircraft nuclear propulsion program to produce superheated steam for marine propulsion.
Date: April 6, 1962
Creator: General Electric Company. Flight Propulsion Division.
System: The UNT Digital Library
Improved Zirconium Alloys Quarterly Report: January - March 1962 (open access)

Improved Zirconium Alloys Quarterly Report: January - March 1962

The following report is one of a series of quarterly reports following the progress and development of improved zirconium alloys for service in superheated water and steam. This report covers the period between January 1 to March 31, 1962 and was conducted by the United States and the European Atomic Energy Community (EURATOM). The major effort in this period has been devoted to ascertaining and evaluating corrosion behavior of 75 ternary compositions.
Date: April 6, 1962
Creator: Weinstein, Daniel & Holtz, F. C.
System: The UNT Digital Library
PT-IP-297-A-FP, The effect of autoclave film damage on the incidence of groove pitting on X-8001 alloy fuel jackets (open access)

PT-IP-297-A-FP, The effect of autoclave film damage on the incidence of groove pitting on X-8001 alloy fuel jackets

The objective of this test is to evaluate the hypothesis that autoclave film damage is a necessary condition for groove pitting of X-8001 alloy fuel cladding.
Date: April 6, 1960
Creator: Hall, R. E.
System: The UNT Digital Library
Daily data sheets -- PT-IP-280 A: Ingot-alloyed dingot D-Reactor (open access)

Daily data sheets -- PT-IP-280 A: Ingot-alloyed dingot D-Reactor

The data consists of out and inlet temperatures, and panellit and header pressures, sorted according to date and tube-pile.
Date: April 6, 1960
Creator: Hall, R. E.
System: The UNT Digital Library
Supplementary report of preliminary testing production test IP-234-AE: Supplement 2, Project CG-775, prototype testing of the 190-K process pumping units (open access)

Supplementary report of preliminary testing production test IP-234-AE: Supplement 2, Project CG-775, prototype testing of the 190-K process pumping units

It was necessary to provide a basis for the design of modifications to the 190-K pumping units to achieve increased process water flow rates. The prototype pumping unit was inspected for cavitation damage after 3 months operation. The low lift pump impeller showed no cavitation damage, while the high lift pump impeller showed excessive damage. The lower max flow capacity and slightly increased power requirements of the third prototype impeller should not preclude its use if its cavitation performance proves satisfactory. Required combined five and six pump flow rates would be achieved with proper sizing of impeller diameter. Adequate margin of safety would exist between design operating points (five and six pump operating points) and max capacity. Under four pump operating conditions, the flow would be reduced 1% below that of the first impeller design, and the bulk outlet temperature surge would be increased one degree following instantaneous reduction to four pump operation.
Date: April 6, 1961
Creator: Schack, M. H.
System: The UNT Digital Library
Production Test IP-502-I calibration of gas monitoring instrumentation to measure the amount of oxygen in a reactor (open access)

Production Test IP-502-I calibration of gas monitoring instrumentation to measure the amount of oxygen in a reactor

This production test is designed to test the feasibility of controlling the amount of air entering a reactor, hence, the burnout of the graphite by monitoring the gas activity. Gas activity comes from the induced activity on argon, which is one of the constituents of air. This production test is basically a test to calibrate the gas activity instruments as a function of various amounts of argon in the reactors gas system. The first two parts of the test are calibration points with different amounts of argon. From these calibration points, extrapolation or interpolation can be used to determine expected activities for other amounts of argon. (GHH)
Date: April 6, 1962
Creator: Smit, W. R.
System: The UNT Digital Library
Process optimization 709 program (open access)

Process optimization 709 program

In the past two years a number of process optimization studies have been made with the aid of IBM machine programs. These programs have been designed to calculate optimum power levels and optimum goal exposures so that better insight could be gained for use in resolving plant operating plans. We feel that this approach has been highly successful. In January of 1960, a new program was written for the IBM 709 to incorporate the desirable features of the previous programs and to provide additional output data. This document is a description of the new programs.
Date: April 6, 1960
Creator: Turner, R. L. & Poor, C. F.
System: The UNT Digital Library
A Plasma Cyclotron (open access)

A Plasma Cyclotron

In a previous report the adaptation of Stix's ion-cyclotron-wave-heating scheme to the mirror geometry was suggested. An experiment along these lines has been conducted for the past year by E. Chambers, using a tubular P.I.G discharge to provide the basic plasma. The Chambers experiment has been eminently successful in demonstrating the transfer of rf power along the P.I.G. (as along a co-axial conductor), and the resultant acceleration of ions. The power transfer is evident from the predominantly resistive rf impedance of the P.I.G. (1 - 10 ohms), the production of intense luminosity outside the dc P.I.G channel when the rf is turned on, and by the observation large signals with magnetic pick-up loops. The ion heating is demonstrated by direct measurement of ion current on a probe some centimeters outside the P.I.G., and by the observation of energetic charge-exchange neutrals. At the same time, the characteristic features of heating by ion-cyclotron-waves, as described by Stix, are only partly in evidence. The visible broadening of the P.I.G. channel and such fast-ion phenomena as neutral emission do seem to be maximal near the expected cyclotron resonance point. However, the rf impedance is anomalous both in magnitude and parameter dependence, and there are …
Date: April 6, 1960
Creator: Furth, Harold P.
System: The UNT Digital Library
Deposition Of Thermal Energy By Nuclear Explosives (open access)

Deposition Of Thermal Energy By Nuclear Explosives

A fraction of the energy released by the underground detonation of nuclear explosives is locally deposited as residual thermal energy. An accurate prediction of this usable fraction of the energy released is necessary to evaluate the feasibility of several of the proposed projects in the Plowshare Program. This paper will present a summary of the available data on residual thermal energy from nuclear detonations in three different geological media: tuff, halite, and granodiorite.
Date: April 6, 1964
Creator: Heckman, Richard A.
System: The UNT Digital Library
Exponential Signal Rate-Of-Rise Measurement Instrument (open access)

Exponential Signal Rate-Of-Rise Measurement Instrument

The increasing exponential function e-at [a > 0] characterizes such natural events as gas discharges, neutron multiplication, and the transistor avalanche phenomenon. This report describes an instrument for measuring the rate of rise, a, of an increasing electrical exponential signal.
Date: April 6, 1964
Creator: Holladay, Gale; Behrin, Ervin & Campbell, Donald
System: The UNT Digital Library