Homogeneous Reactor Project Quarterly Progress Report for Period Ending July 31, 1955 (open access)

Homogeneous Reactor Project Quarterly Progress Report for Period Ending July 31, 1955

Construction of the HRT reactor shield tank was completed, and the inside surfaces were painted. The roof structure for the tank is being assembled in preparation for an acceptance pressure test. Service piping and instrument lines are being installed in the central room area by ORNL craft forces. This work is approximately 50% complete. Fabrication of all temperature system components, except the blanket outer storage tanks, has been completed.
Date: October 10, 1955
Creator: McDuffie, H. F. & Kelly, D. C.