105-K east sandfilter backwash line sample analysis report. Second campaign (open access)

105-K east sandfilter backwash line sample analysis report. Second campaign

This project seeks to produce uranium (U) and plutonium (Pu) analyses of samples taken from the KE basin filter backwash line each time the sand filter is backwashed. K Basin operations will use the analytical results to determine additions of fissile materials to the backwash sludge pit and thereby maintain a running inventory of fissile elements in the pit. K Basin Operations must not exceed a certain total inventory in order to be within a criticality specification. The second campaign of this project consisted of three samples, numbered by the customer 208KEB, 209KEB, and 210KEB.
Date: January 25, 1996
Creator: Miller, George L.
Object Type: Report
System: The UNT Digital Library
105-K east sandfilter backwash line sample analysis report: Third campaign (open access)

105-K east sandfilter backwash line sample analysis report: Third campaign

This project seeks to produce uranium (U) and plutonium (Pu) analyses of samples taken from the KE basin filter backwash line each time the sand filter is backwashed. K Basin operations will use the analytical results to determine additions of fissile materials to the backwash sludge pit and thereby maintain a running inventory of fissile elements in the pit. K Basin operations must not exceed a certain total inventory in order to be within a criticality specification. The third campaign of this project consisted of three samples, numbered by the customer 245KEB, 246KEB, and 247KEB. A revised letter of instruction controlled their processing.
Date: January 25, 1996
Creator: Miller, George L. & Bechtold, D. B.
Object Type: Report
System: The UNT Digital Library
Contract reform: It`s working at Fernald (open access)

Contract reform: It`s working at Fernald

DOE`s contract reform initiatives at Fernald and the performance-based system DOE is now using to evaluate FERMCO are key elements to the current and future success of DOE and FERMCO at Fernald. Final cleanup of the Fernald site is planned for completion by 2005 per an accelerated 10-year remediation plan which has been approved by DOE and endorsed by the US EPA, Ohio EPA, and the Fernald Citizens Task Force. Required funding of approximately $276 million plus inflation annually for 10 years to accomplish final cleanup is now being considered by US Congress. Contract reform initiatives and modified performance measurement systems, along with best business practices, are clearing the path for the expedited cleanup of Fernald.
Date: January 25, 1996
Creator: Craig, J. & Hunt, A.
Object Type: Article
System: The UNT Digital Library
Functions and requirements for the light duty utility arm integrated system (open access)

Functions and requirements for the light duty utility arm integrated system

The Light Duty Utility Arm (LDUA) Integrated System is a mobile robotic system designed to remotely deploy and operate a variety of tools in uninhabitable underground radiological and hazardous waste storage tanks. The system primarily provides a means to inspect, survey, monitor, map and/or obtain specific waste and waste tank data in support of the Tank Waste Remediation System (TWRS) mission at Hanford and remediation programs at other U.S. Department of Energy (DOE) sites.
Date: January 25, 1996
Creator: Kiebel, G.R.
Object Type: Report
System: The UNT Digital Library
Functions and requirements for the Light-Duty Utility Arm Integrated System. Revision 1 (open access)

Functions and requirements for the Light-Duty Utility Arm Integrated System. Revision 1

The Light Duty Utility Arm (LDUA) Integrated System is a mobile robotic system designed to remotely deploy and operate a variety of tools in uninhabitable underground radiological and hazardous waste storage tanks. The system primarily provides a means to inspect, survey, monitor, map and/or obtain specific waste and waste tank data in support of the Tank Waste Remediation System (TWRS) mission at Hanford and remediation programs at other U.S. Department of Energy (DOE) sites.
Date: January 25, 1996
Creator: Kiebel, G.R.
Object Type: Report
System: The UNT Digital Library
Hazard categorization of 105-KE basin debris removal project (open access)

Hazard categorization of 105-KE basin debris removal project

This supporting document provides the hazard categorization for 105-KE Basin Debris Removal Project activities planned in the K east Basin. All activities are categorized as less than Hazard Category 3.
Date: January 25, 1996
Creator: Meichle, R.H.
Object Type: Report
System: The UNT Digital Library
Interim safety equipment list for 241-C-106 waste retrieval, project W-320 (open access)

Interim safety equipment list for 241-C-106 waste retrieval, project W-320

The purpose of this supporting document is to provide safety classifications for systems, structures, and components of the Tank 241-C-106 Waste Retrieval Sluicing System (WRSS) and to document the methodology used to develop these safety classifications. The WRSS requires two transfer lines, one to carry sluiced waste slurry to tank 241-AY-102 and the other to return supernatant to tank 241-C-106; pumps in each tank; sluicers to direct the supernatant stream inside tank 241-C-106; a slurry distributor in tank 241-AY-102; heating, ventilation, and air conditioning for tank 241-C-106; and instrumentation and control devices.
Date: January 25, 1996
Creator: Conner, J. C.
Object Type: Report
System: The UNT Digital Library
Mechanisms of flow through compressible porous beds in sedimentation, centrifugation, deliquoring, and ceramic processing (open access)

Mechanisms of flow through compressible porous beds in sedimentation, centrifugation, deliquoring, and ceramic processing

The major topics covered in the investigation include: centrifugation; cake filtration; sedimentation and thickening; capillary suction operations; ceramics, slip casting; optimization studies; and wastewater. The research program was aimed at the specific areas of solid/liquid separation including sedimentation, thickening, cake filtration, centrifugation, expression, washing, deep-bed filtration, screening, and membrane separation. Unification of the theoretical approaches to the various solid/liquid separation operations was the principle objective of the research. Exploring new aspects of basic separation mechanisms, verification of theory with experiment, development of laboratory procedures for obtaining data for design, optimizing operational methods, and transferring the results to industry were part of the program.
Date: January 25, 1996
Creator: unknown
Object Type: Report
System: The UNT Digital Library
Modeling a novel glass immobilization waste treatment process using flow (open access)

Modeling a novel glass immobilization waste treatment process using flow

One option for control and disposal of surplus fissile materials is the Glass Material Oxidation and Dissolution System (GMODS), a process developed at ORNL for directly converting Pu-bearing material into a durable high-quality glass waste form. This paper presents a preliminary assessment of the GMODS process flowsheet using FLOW, a chemical process simulator. The simulation showed that the glass chemistry postulated ion the models has acceptable levels of risks.
Date: January 25, 1996
Creator: Ferrada, J. J.; Nehls, Jr., J. W.; Welch, T. D. & Giardina, J. L.
Object Type: Article
System: The UNT Digital Library
NORTH PORTAL - DOMESTIC COLD WATER CALCULATION - CHANGE HOUSE FACILITY #5008 (open access)

NORTH PORTAL - DOMESTIC COLD WATER CALCULATION - CHANGE HOUSE FACILITY #5008

The purpose of this design analysis and calculation is to determine the demand for domestic cold water and to size the supply main piping for the Change House Facility No.5008 in accordance with the Uniform Plumbing Code (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540 (Section 4.4.2). The method used for the calculations is based on the Uniform Plumbing Code (UPC), Section 4.4.1. The first step is to determine the maximum pressure drop between the most remote cold water plumbing fixture and the main distribution supply. The developed length of pipe from the supply to the fixture is then determined from the plumbing drawings. The maximum pressure drop is then divided by the developed length which results in the friction loss per 100 feet of pipe. Equivalent fixture units are assigned from the UPC based on the actual fixture count which when totaled determines the water flow rate. The water flow rate and pressure drop are used to determine the pipe size based on a given velocity of flow.
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL - HOT WATER CALCULATION - CHANGE HOUSE FACILITY #5008 (open access)

NORTH PORTAL - HOT WATER CALCULATION - CHANGE HOUSE FACILITY #5008

The purpose of this design analysis and calculation is to determine the demand for hot water and to size the supply main piping for the Change House Facility No.5008 in accordance with the Uniform Plumbing Code (UPC) (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540. The method used for the calculations is based on Section 4.4.1. The first step is to determine the maximum pressure drop between the most remote plumbing fixture and the main supply. The pressure drop for the hot water system is based on the total length of the supply piping from the cold water supply source through the water heater to the most remote hot water outlet. Equivalent fixture units are then assigned using Section 4.4.1. For hot water, the values are reduced by 25 percent in accordance with the UPC. The demand load in gpm is then determined based on the number of fixture units. The demand load and the pressure drop between the source and the most remote fixture is used to determine the pipe size and the corresponding friction losses for a given flow velocity not to exceed 10 feet/second.
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL - HOT WATER CIRCULATION PUMP CALCULATION - CHANGE HOUSE FACILITY #5008 (open access)

NORTH PORTAL - HOT WATER CIRCULATION PUMP CALCULATION - CHANGE HOUSE FACILITY #5008

The purpose of this design analysis and calculation is to size and select a circulating pump for the Change House Facility hot water system.
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL - HOT WATER CIRCULATION PUMP CALCULATION - SHOP BUILDING #5006 (open access)

NORTH PORTAL - HOT WATER CIRCULATION PUMP CALCULATION - SHOP BUILDING #5006

None
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL-HOT WATER CIRCULATION PUMP CALCULATION-SHOP BUILDING #5006 (open access)

NORTH PORTAL-HOT WATER CIRCULATION PUMP CALCULATION-SHOP BUILDING #5006

The purpose of this design analysis and calculation is to size a circulating pump for the service hot water system in the Shop Building 5006, in accordance with the Uniform Plumbing Code (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540 (Section 4.4.2). The method used for the calculation is based on Reference 5.2. This consists of determining the total heat transfer from the service hot water system piping to the surrounding environment. The heat transfer is then used to define the total pumping capacity based on a given temperature change in the circulating hot water as it flows through the closed loop piping system. The total pumping capacity is used to select a pump model from manufacturer's literature. This established the head generation for that capacity and particular pump model. The total length of all hot water supply and return piping including fittings is then estimated from the plumbing drawings which defines the pipe friction losses that must fit within the available pump head. Several iterations may be required before a pump can be selected that satisfies the head-capacity requirements.
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL - SANITARY SEWER CALCULATION - CHANGE HOUSE FACILITY #5008 (open access)

NORTH PORTAL - SANITARY SEWER CALCULATION - CHANGE HOUSE FACILITY #5008

The purpose of this design calculation is to determine the demand on the waste system and to size the three main sanitary sewer lines serving the Change House Facility No.5008, in accordance with the Uniform Plumbing Code (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540 (Section 4.4.2).
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL - WATER HEATER CALCULATION - CHANGE HOUSE FACILITY #5008 (open access)

NORTH PORTAL - WATER HEATER CALCULATION - CHANGE HOUSE FACILITY #5008

The purpose of this design analysis and calculation is to determine the demand for hot water in the Change House Facility and the selection of a water heater of appropriate size in accordance with the Uniform Plumbing Code (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540 (Section 4.4.2).
Date: January 25, 1996
Creator: Blackstone, R.B.
Object Type: Report
System: The UNT Digital Library
NORTH PORTAL-WATER HEATER CALCULATION-SHOP BUILDING #5006 (open access)

NORTH PORTAL-WATER HEATER CALCULATION-SHOP BUILDING #5006

The purpose of this design analysis and calculation is to determine the demand for hot and the selection of a water heater of appropriate size, in accordance with the Uniform Plumbing Code (Section 4.4.1) and U.S. Department of Energy Order 6430.1A-1540 (Section 4.4.2).
Date: January 25, 1996
Creator: Blackstone, R.
Object Type: Report
System: The UNT Digital Library
Texas Attorney General Opinion: DM-374 (open access)

Texas Attorney General Opinion: DM-374

Document issued by the Office of the Attorney General of Texas in Austin, Texas, providing an interpretation of Texas law. It provides the opinion of the Texas Attorney General, Dan Morales, regarding a legal question submitted for clarification; Whether the El Paso County Water Improvement District No. 1 may, pursuant to chapter 55, subchapter N of the Water Code, assess a tax on the benefit basis against land belonging to the Permanent University Fund (RQ-715)
Date: January 25, 1996
Creator: Texas. Attorney-General's Office.
Object Type: Text
System: The Portal to Texas History
Texas Attorney General Opinion: LO96-008 (open access)

Texas Attorney General Opinion: LO96-008

Letter opinion issued by the Office of the Attorney General of Texas in Austin, Texas, providing an interpretation of Texas law. It provides the opinion of the Texas Attorney General, Dan Morales, regarding a legal question submitted for clarification; Whether the Houston Metropolitan Transit Authority may provide buses for use during the 1996 Olympic Games un Atlanta (ID# 38134)
Date: January 25, 1996
Creator: Texas. Attorney-General's Office.
Object Type: Text
System: The Portal to Texas History
Using systems analysis to improve decision making in solving mixed waste problems at the Oak Ridge National Laboratory (ORNL) (open access)

Using systems analysis to improve decision making in solving mixed waste problems at the Oak Ridge National Laboratory (ORNL)

ORNL has accumulated considerable quantitites of mixed wastes, many containing hazardous and radioactive components. Finding a suitable technique for treating mixed wastes is a challenging task. The Federal Facilities Compliance Act requires ODE to provide on-site treatment plans. A method of analysis was needed for quick, easy trade-off studies and alternatives evaluations. Evaluation of ORO management of mixed waste indicated that a systems analysis, including development of automated analysis tools and integrated models, was required. Integrated systems approach was needed because of the complexity. Risk, cost, performance, and uncertainty were considered. Resuts produced in these studies may be refined as more nearly accurate information is obtained about uncertanties in some treatment alternative.
Date: January 25, 1996
Creator: Ferrada, J. J.; Welch, T. D.; Osborne-Lee, I. W. & Nehls, Jr., J. W.
Object Type: Article
System: The UNT Digital Library
Winter Fuels Report: Week Ending January 19, 1996 (open access)

Winter Fuels Report: Week Ending January 19, 1996

The Winter Fuels Report is intended to provide concise, timely information to the industry, the press, the policymakers, consumers, analysts, and State and local governments on the following topics: distillate fuel oil net production, imports and stocks on a US level and for all Petroleum Administration for Defense Districts (PADD) and product supplied on a US level; propane net production, imports and stocks on a US level and for PADD`s 1, 2, and 3; natural gas supply and disposition and underground storage for the US and consumption for all PADD`s, as well as selected National average prices; residential and wholesale pricing data for heating oil and propane for those States participating in the joint Energy Information Administration (EIA)/State Heating Oil and Propane Program; crude oil and petroleum price comparisons for the US and selected cities; and a 6--10 Day and 30-Day outlook for temperature and precipitation and US total heating degree-days by city. 36 figs., 13 tabs.
Date: January 25, 1996
Creator: unknown
Object Type: Report
System: The UNT Digital Library
Mechanical charactization of sonar window materials (open access)

Mechanical charactization of sonar window materials

The three-dimensional mechanical behavior of thick Spectra/epoxy sonar window materials containing various special materials is summarized in this report. Three different materials, which were fabricated by two companies known as `A` and `B` were received from the Naval Warfare Center. The three materials designated `A with microspheres (A micron),` `A without microspheres (A),` and `B` were measured for all properties. The total number of tests was reduced through the assumption that the two orthogonal, in-place directions were identical. Consequently, these materials should have only six independent elastic variables. The measured constants and strengths are given.
Date: March 25, 1996
Creator: DeTeresa, S. J.; Groves, S. E.; Harwood, P. J. & Sanchez, R. J.
Object Type: Report
System: The UNT Digital Library
Natural Gas Monthly, March 1996 (open access)

Natural Gas Monthly, March 1996

The Natural Gas Monthly (NGM) highlights activities, events, and analyses of interest to public and private sector organizations associated with the natural gas industry. Volume and price data are presented each month for natural gas production, distribution, consumption, and interstate pipeline activities. Producer-related activities and underground storage data are also reported. From time to time, the NGM features articles designed to assist readers in using and interpreting natural gas information.
Date: March 25, 1996
Creator: unknown
Object Type: Report
System: The UNT Digital Library
Slag characterization and removal using pulse detonation for coal gasification. Quarterly research report, January 1, 1996--March 31, 1996 (open access)

Slag characterization and removal using pulse detonation for coal gasification. Quarterly research report, January 1, 1996--March 31, 1996

Microbeam Technologies Incorporated (MTI) is working with Prairie View to develop and demonstrate a new method to remove deposits from coal-fired utility boilers. MTI is providing background information on fuel properties, ash formation, ash deposition, and ash removal. In addition, MTI is providing deposits collected from a full scale utility boilers. Ash deposits on fireside heat exchange surfaces of power plants significantly decrease plant efficiency and are aggravated by variability in coal quality. Deposit formation is related to coal quality (chemical and physical characteristics of the inorganic material), system operating conditions, and system design. Variations in coal quality can significantly influence ash deposition on heat transfer surfaces resulting in decreased plant performance and availability. Ash accumulations on heat transfer surfaces require annual or semi-annual shutdowns for cleaning which result in cleaning costs and lost revenues from being off-line. In addition, maintaining slag flow in wet bottom boilers and cyclone-fired boilers can require co-firing of other fuels and outages to remove frozen slag resulting in decreased efficiency and availability. During this reporting period MTI performed analysis of deposits collected from full-scale utility boilers. Deposit samples were obtained from Basin Electric and from Northern States Power (NSP). The analyses were conducted using …
Date: March 25, 1996
Creator: Huque, Z.; Mei, D.; Biney, P.O. & Zhou, J.
Object Type: Report
System: The UNT Digital Library