Proposed Ground Water Protection Strategy for the Uranium Mill Tailings Site at Green River, Utah. Final Report (open access)

Proposed Ground Water Protection Strategy for the Uranium Mill Tailings Site at Green River, Utah. Final Report

This document presents the US DOE water resources protection strategy for the Green River, Utah mill tailings disposal site. The modifications in the original plan are based on new information, including ground water quality data collected after remedial action was completed, and on a revised assessment of disposal cell design features, surface conditions, and site hydrogeology. All aspects are discussed in this report.
Date: November 1994
Creator: unknown
System: The UNT Digital Library
Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Near Green River, Utah (open access)

Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Near Green River, Utah

This document evaluates potential impacts to public health and the environment resulting from ground water contamination at the former uranium mill processing site. The tailings and other contaminated material at this site were placed in a disposal cell on the site in 1989 by the US DOE`s Uranium Mill Tailings Remedial Action (UMTRA) Project. Currently, UMTRA Project is evaluating ground water contamination in this risk assessment.
Date: September 1994
Creator: unknown
System: The UNT Digital Library
Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Salt Lake City, Utah (open access)

Baseline Risk Assessment of Ground Water Contamination at the Uranium Mill Tailings Site Salt Lake City, Utah

This baseline risk assessment of groundwater contamination at the uranium mill tailings site near Salt Lake City, Utah, evaluates potential public health or environmental impacts resulting from ground water contamination at the former uranium ore processing site. The tailings and other contaminated material at this site were placed in a disposal cell located at Clive, Utah, in 1987 by the US Department of Energy`s Uranium Mill Tailings Remedial Action (UMTRA) Project. The second phase of the UMTRA Project is to evaluate residual ground water contamination at the former uranium processing site, known as the Vitro processing site. This risk assessment is the first site-specific document under the Ground Water Project. It will help determine the appropriate remedial action for contaminated ground water at the site.
Date: September 1994
Creator: unknown
System: The UNT Digital Library
UMTRA Project Site Observational Work Plan, Mexican Hat, Utah (open access)

UMTRA Project Site Observational Work Plan, Mexican Hat, Utah

Surface cleanup activities at the Mexican Hat UMTRA processing site are nearing completion. Ground Water contamination at the Mexican Hat site is a result of uranium milling operations. The extent of residual process water has been identified, and it is limited to the uppermost aquifer in the vicinity of the site. Deeper aquifers are not affected because of an upward hydraulic gradient and the presence of a confining unit (the deeper aquifers are protected by hydrogeologic isolation). The uppermost unit is returning to its pre-milling, mainly unsaturated state. The unit that contains the contaminated water is not a ground water resource because it qualifies as Class III (limited use) based on limited yield. Ground water in the uppermost unit is currently not used and is not anticipated to be used as a ground water resource. The nearby San Juan River and a converted oil exploration well provide all of the water needs for the area. There are no current threats to human health or livestock; and, because the zone of contamination does not represent a ground water resource, none are anticipated in the future. There are, however, seeps where contaminated water is exposed at land surface. The seeps create potential …
Date: September 1994
Creator: unknown
System: The UNT Digital Library
UMTRA Project Water Sampling and Analysis Plan, Mexican Hat, Utah (open access)

UMTRA Project Water Sampling and Analysis Plan, Mexican Hat, Utah

The Mexican Hat, Utah, Uranium Mill Tailings Remedial Action (UMTRA) Project site is a former uranium mill that is undergoing surface remediation in the form of on-site tailings stabilization. Contaminated surface materials from the Monument Valley, Arizona, UMTRA Project site have been transported to the Mexican Hat site and are being consolidated with the Mexican Hat tailings. The scheduled completion of the tailings disposal cell is August 1995. Water is found in two geologic units at the site: the Halgaito Shale Formation and the Honaker Trail Formation. The tailings rest on the Halgaito Shale, and water contained in that unit is a result of milling activities and, to a lesser extent, water released from the tailings from compaction during remedial action construction of the disposal cell. Water in the Halgaito Shale flows through fractures and discharges at seeps along nearby arroyos. Flow from the seeps will diminish as water drains from the unit. Ground water in the lower unit, the Honaker Trail Formation, is protected from contamination by an upward hydraulic gradient. There are no nearby water supply wells because of widespread poor background ground water quality and quantity, and the San Juan River shows no impacts from the site. …
Date: April 1994
Creator: unknown
System: The UNT Digital Library