Concrete Placing

Caption says, "A-976 Erecting forms and placing concrete in canal outletworks stilling basin at Altus Dam."
Date: January 23, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Concrete Placing

Caption says, "A-975 Placing concrete in Altus Dam at Elevation 1548, above canal Outletworks."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Completed Section of Main Canal

Caption says, "A-979 View of completed section of Main Canal, looking downstream from Station 190."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Completed Siphon

Caption says, "A-977 View of completed siphon under A.T. & S.F. Ry. showing outlet transition, Main Canal Station 55+73."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Main Canal Excavation

Caption says, "A-978 View looking upstream from Station 160 of Main Canal showing Northwest shovel and trucks excavating canal, and roller compacting canal embankment."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Main Canal Construction Progress

Caption says, "A-980 General view of construction progress on Main Canal siphon across North Fork of Red River, taken from near Station 97. The river is being diverted through channel over completed section of siphon barrel in center of picture. The regular river channel formerly crossed the siphon location in the foreground."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History

Prepping to Jack Bridge

Caption says, "A-974 Driving piling in preparation for jacking up bridge spans on C.R.I & P. Ry. reconstruction across upper part of revervoir area. Shoofly track and bridge are in place at left side of picture."
Date: January 22, 1945
Creator: George, P. W.
System: The Gateway to Oklahoma History