Floodwater Retarding Structure Site No. 9

Photograph of site no. 9, Owl Creek subwatershed of the Washita River. Construction work completed on June 20, 1956 by the Paul R. Moody Construction Co. , Contractor. Drainage area 404 acres. Sediment pool storage 17 acre feet. Flood pool storage 155 acre feet. Estimated cost $21,838. 00. Benefit cost ratio 1. 92:1. From the west end of the embankment looking NE.
Date: July 21, 1956
Creator: McCray, V. H.
System: The Gateway to Oklahoma History

Floodwater Retarding Structure Site No. 10

Photograph of Site 10, Owl Creek subwatershed of the Washita River. Work started on 2-28-56 and was completed on 6-20-56 by the Paul R. Moody Construction Co. of Pauls Valley, Okla. Drainage area 303 acres, sediment pool storage 20 acre feet, sediment pool area 5 acres, flood pool storage 115. 5 acre feet, estimated cost $17,319. 00, annual benefit to the downstream flood plain $1,222. 00, benefit cost ratio of 1. 77/1. Earth spillway in background with drawdown structure near the center of the picture.
Date: July 21, 1956
Creator: McCray, V. H.
System: The Gateway to Oklahoma History