FY11 Level-2 Milestone 3953: TLCC2 contract awarded (open access)

FY11 Level-2 Milestone 3953: TLCC2 contract awarded

This report documents completion of FY11 L2 milestone No.3953-TLCC2 contract award. This milestone was scheduled for completion on 3/31/11 and was completed on 4/14/11. There is a separate milestone (3856), due at the end of the fiscal year, concerned with installation of the first LLNL SU and early user access. Efforts related to this tri-lab L2 milestone started early in 2010 with the development of tri-lab requirements for the second ASC capacity system procurement. The SOW was then developed along with necessary RFP paperwork and sent to HQ/DOE for their review prior to being released. There was significant delay in getting this step completed which led to this milestone being put at risk for several months. However, once the RFP was approved and released we were able to get the procurement back on track with aggressive proposal response and review timelines.
Date: September 12, 2011
Creator: Carnes, B