100 Areas, July 23 through July 29. For technical progress letter number 108 (open access)

100 Areas, July 23 through July 29. For technical progress letter number 108

The weekly progress for D and F piles is given. Status of the test to determine the cause of white deposits on the horizontal control rods of the F pile is given. Also discussed are studies of process water control and pressure drop, corrosion, and graphite expansion. Test results indicate that graphite expansion has not seriously limited discharge of process tubes.
Date: August 2, 1946
Creator: Jordan, W. E.
System: The UNT Digital Library
Production Test No. 305-9-P, poisoning effectiveness and uniformity of myrnalloy slugs. Final report (open access)

Production Test No. 305-9-P, poisoning effectiveness and uniformity of myrnalloy slugs. Final report

This report discusses the poisoning effectiveness and uniformity of the first production batch of 33 myrnalloy slugs which was tested in the 305 Test Pile on February 26, 1946, prior to charging into the D Pile in accordance with Production Test No. 105-49-P, supplement A.
Date: April 2, 1946
Creator: Wende, C. W. J.