100-300 Area program meeting of May 7, 1946 (open access)

100-300 Area program meeting of May 7, 1946

None
Date: May 7, 1946
Creator: Kidder, C. P.
Object Type: Report
System: The UNT Digital Library
100 Areas: April 9--April 15 (open access)

100 Areas: April 9--April 15

Reported are: physics (B Pile, D Pile, F Pile, general physics); and water, corrosion, and engineering (process water control and pressure drop studies, purging studies, corrosion, graphite expansion, downcomer -- B Area).
Date: April 19, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: April 16--April 22 (open access)

100 Areas: April 16--April 22

Reported are: physics (B pile, D pile, F pile, general physics); and water, corrosion and engineering (process water control and pressure drop studies, purging studies, removal of process tube B-3671).
Date: April 26, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas, February 5--February 11 (open access)

100 Areas, February 5--February 11

This report gives the weekly status for the B, D, and F piles. Also given is the reactivity status at the end of the week for each pile. Process water control and pressure drop studies are discussed. Finally a brief discussion is given of the graphite expansion problem.
Date: February 15, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 95), April 23--29 (open access)

100 Areas: (For technical progress letter No. 95), April 23--29

Reported are: physics (B Pile, D Pile, F Pile, general physics); and water, corrosion and engineering (process water control and pressure drop studies, corrosion, graphite expansion).
Date: May 3, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 96), April 30--May 6 (open access)

100 Areas: (For Technical Progress Letter No. 96), April 30--May 6

None
Date: May 10, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 97), May 7--13 (open access)

100 Areas: (For Technical Progress Letter No. 97), May 7--13

Physics information for the D and F piles is presented. Thermal conductivity, reactivity, and irradiation levels are included. Concerning the cooling systems: process water control, pressure drip studies, purging studies, corrosion, and gun barrel clearance of expanded graphite are discussed. (GHH)
Date: May 17, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 98), May 14--May 20 (open access)

100 Areas: (For technical progress letter No. 98), May 14--May 20

This technical progress report details 100 Area activities for the time period of May 14 through May 20, 1946.
Date: May 24, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 99), May 21--May 27 (open access)

100 Areas: (For technical progress letter No. 99), May 21--May 27

This report details 100 Area reactor operation for the time period of May 21 through May 27, 1946.
Date: May 31, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 101), June 4--10 (open access)

100 Areas: (For Technical Progress Letter No. 101), June 4--10

None
Date: June 14, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 102), June 11--June 17 (open access)

100 Areas: (For Technical Progress Letter No. 102), June 11--June 17

Operation of the D and F Piles is reported. Other items reported are: general; water, corrosion and engineering (graphite expansion).
Date: June 21, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 104), June 25--July 1 (open access)

100 Areas: (For technical progress letter No. 104), June 25--July 1

None
Date: July 5, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 107), July 16--22 (open access)

100 Areas: (For Technical Progress Letter No. 107), July 16--22

This technical progress report details 100 Area activities for the time period of July 16 through July 22, 1946.
Date: July 26, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For Technical Progress Letter No. 109), July 30--August 5 (open access)

100 Areas: (For Technical Progress Letter No. 109), July 30--August 5

None
Date: August 9, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 110), August 6--August 12 (open access)

100 Areas: (For technical progress letter No. 110), August 6--August 12

This report details 100 Area reactor operation for the time period of August 6 through August 12, 1946.
Date: August 16, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas: (For technical progress letter No. 111), August 13--August 19 (open access)

100 Areas: (For technical progress letter No. 111), August 13--August 19

This technical progress report details 100 Area activities for the time period of August 13 through August 19, 1946.
Date: August 23, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas, January 1 through January 7, 1946 (open access)

100 Areas, January 1 through January 7, 1946

During this period the B Pile operated at its assigned power level of 25 MW below rated level, except for 10 hours on January 5. The operating level of the D Pile remained at 25 MW below rating. The rate gain in excess reactivity during equilibrium operation has been about 1.8 inhours/day. On January 1, the power level of the F Pile was dropped to 25 MW below rating from its previous rated level. Rod A was in a favorable position to make a determination of the reactivity coefficients at the time. The data does indicate an upper limit of {minus}0.21 ih/MW for the metal coefficient. An overall coefficient of 0.20 ih/MW was obtained. The unit was shut down on January 3 for discharge of 129 tubes of metal. A summary of the present reactivity states of the B, D, and F Piles are given. Iron content of process water for the three piles is also given.
Date: January 11, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas, January 15 through January 21 (open access)

100 Areas, January 15 through January 21

This report gives the weekly progress for the B, D, and F piles. The report also gives a brief discussion of the following activities: process water control and pressure drop studies; purging of D, B, and F piles; slug corrosion studies; tube corrosion studies; thimble corrosion studies; and graphite expansion studies.
Date: January 25, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas, January 29 through February 4, 1946 (open access)

100 Areas, January 29 through February 4, 1946

The B Pile operated 25 MW below rated power level without interruption during the week. The D Pile was shut down on January 29. During the shutdown 103 tubes were discharged. The shut down lasted for 15 hours. During operation after the shut down power was reduced to meet graphite temperature restrictions. The F Pile was run steadily throughout the week at 25 MW below rated level. Iron content in the process water averaged 0.015, 0.011 and 0.010 ppm at B, D, and F Areas, respectively. Examination of the slugs discharged from four corrosion tubes at F has been completed. A summary of conditions found in the vertical and horizontal aluminium thimbles at D and F during a recent inspection are given. Results are given on the graphite expansion problem.
Date: February 8, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas, July 23 through July 29. For technical progress letter number 108 (open access)

100 Areas, July 23 through July 29. For technical progress letter number 108

The weekly progress for D and F piles is given. Status of the test to determine the cause of white deposits on the horizontal control rods of the F pile is given. Also discussed are studies of process water control and pressure drop, corrosion, and graphite expansion. Test results indicate that graphite expansion has not seriously limited discharge of process tubes.
Date: August 2, 1946
Creator: Jordan, W. E.
Object Type: Report
System: The UNT Digital Library
100 Areas technical activities report -- Physics, November 1946 (open access)

100 Areas technical activities report -- Physics, November 1946

This report divides the activities for November into three sections: D Pile; F Pile; and general physics. During November the D Pile was down twice for regularly scheduled shutdowns. Two scram occurred during the month, both of short duration. Five Special Request 15 tubes were discharged and recharged with Special Request 15. Some 13 inhour of reactivity were gained during the month. Vertical rod thimbles, 10 through 22, were tested. A Production Test was performed to determine the reactivity power coefficients of the F Pile at low power levels and with practically no xenon poison remaining. Additional experience in the use of temporary poison columns during an extended shutdown of the pile was obtained during the month. Four new bismuth columns were charged during the month and six tubes were charged with LiF. The F Pile had not yet returned to xenon equilibrium following the shutdown of November 27 at the end of the month, but conditions just prior to this shutdown indicate a loss of one inhour since October 31. Two sets of specimens were removed from the ``B`` Test Hole of the F Pile on November 4. Samples were also machined from graphite removed from the No. 9 …
Date: December 11, 1946
Creator: Gast, P. F.
Object Type: Report
System: The UNT Digital Library
100 Areas technical activities report -- Physics, October 1946 (open access)

100 Areas technical activities report -- Physics, October 1946

The D Pile was down five times for scheduled shutdowns. The fifth shutdown was of short duration for the purpose of discharging temporary ``P`` columns. Details of the shutdowns are given. Three new bismuth columns were established, Special Requests were charged into seven tubes and three Special Requests were discharged. Three tubes were charged with four-inch slugs. The power level of the F Pile has been corrected for the discrepancy noted last month. Material for irradiation under the Special Request program was charged into six tubes and the B experimental hole during the month. The effect of poison columns and rods on the temperature distribution of the pile was checked for the overall content of the pile. The F Pile gained two in hours in cold, clean reactivity during the month if allowance is made for xenon poison values corresponding to 190 MW for the beginning of the month and 200 MW at the end of the month. The graphite stringer removed from the ``D`` test hole of the D Pile on 3-12-46 was studied physical radiation effects.
Date: November 6, 1946
Creator: Gast, P. F.
Object Type: Report
System: The UNT Digital Library
100 Areas technical activities report - physics, September 1946 (open access)

100 Areas technical activities report - physics, September 1946

The Pine unit was down four times during the month. These were all regularly scheduled shutdowns. Times down vary from 16.9 hours to 19.2 hours. A total of 33.4 tons of metal was discharged. The galvano-meter chamber in experimental hole {open_quotes}A{close_quotes} was replaced. One Special Request was discharged and three tubes have been loaded with Special Request samples. A new bismuth column has been established. Some difficulty has been experienced with high temperatures of both tube exit water and graphite following startup. On one occasion the normal operating level was exceeded for a short period of time.
Date: October 9, 1946
Creator: Montgomery, E. B.
Object Type: Report
System: The UNT Digital Library
100 Areas technical progress letter No. 105, July 2--July 8 (open access)

100 Areas technical progress letter No. 105, July 2--July 8

The physics of the shutdown of the D pile on July 2 is emphasized in the operation report. The F pile shutdown and operating specifics are also discussed. Water, corrosion, and engineering are reported for the B, D, and F areas.