SM-2 Final Design Progress Review Report: December 16, 1959 to March 1, 1960 (open access)

SM-2 Final Design Progress Review Report: December 16, 1959 to March 1, 1960

From introduction: "The contract covers final design of the SM-2 Nuclear Power (PWR) Steam Electric Station, described in the preliminary design report, APAE 40, Volumes I and II."
Date: April 6, 1960
Creator: Knighton, G. W.
System: The UNT Digital Library
Gas-Cooled Reactor Project Quarterly Progress Report: December 1961 (open access)

Gas-Cooled Reactor Project Quarterly Progress Report: December 1961

Report documenting ongoing research and developments at the Oak Ridge National Laboratory's Gas-Cooled Reactor Project.
Date: April 6, 1962
Creator: Oak Ridge National Laboratory
System: The UNT Digital Library