Removal of ruptured slug from tube 3276-DR (open access)

Removal of ruptured slug from tube 3276-DR

None
Date: October 29, 1951
Creator: unknown
System: The UNT Digital Library
G.E. Co. Hanford Works - Project C-431-A production facility - Sec. A, subcontract G-363, revised design report (open access)

G.E. Co. Hanford Works - Project C-431-A production facility - Sec. A, subcontract G-363, revised design report

The 100-C project is to be located adjacent to the present 100-P Area. It is planned to build an addition to the present 181-B River Pump House using the same elevations for pump settings, intakes, and floors as for the present pump house, thus maintaining the same suction conditions and flood protection as B Area. The 105 Building will be located on higher ground than B Area and, therefore, protection against possible flood damage is assured.
Date: March 29, 1951
Creator: unknown
System: The UNT Digital Library
General Electric Company Hanford Works, Project C-431-A Production Facility-Section A, design report (open access)

General Electric Company Hanford Works, Project C-431-A Production Facility-Section A, design report

The 100-C project is to be located adjacent to the present 100-B Area. It is planned to build an addition to the present 181-B river pump house using the same elevations for pump settings, intakes, and floors as for the present pump house, thus maintaining the same suction conditions and flood protection as B Area. The 105 Building will be located on higher ground than B Area and therefore, protection against possible flood damage is assured. This report is divided into the following sections: (1) general description of project; (2) addition to existing river pump house; (3) raw water lines from 181-B addition to 183-C lead house; (4) the 183-C filter plant; (5) 190-C process pump house; (6) power house addition; (7) high tanks; (8) retention basins; (9) outside streamlines; (10) primary substation; (11) outside underground lines; (12) outside electric lines; (13) roads, railroads, walks, fences; (14) structural design of all buildings; and (15) architectural design of all buildings.
Date: March 29, 1951
Creator: Colburn, R. T.
System: The UNT Digital Library
Process considerations additional product concentration facilities in 202-S (open access)

Process considerations additional product concentration facilities in 202-S

This memorandum discusses investigations concerning the coupling step required to adapt a Redox IIBP to a 234-5 feed which have indicated that a single peroxide strike from a solution 50--60 g./1. in product and about 2 M in nitric acid is adequate. Additional work is planned to demonstrate both peroxide and Pu(IV) oxalate strikes under these conditions. The present Redox PR cage product contains 10 g./1. in product and over 500 g./1. in nitric acid, and probably requires tow peroxide strikes; in addition, the operating capacity of the PR cage may be inadequate to process the throughputs desired in the Redox plant. A two stage continuous concentration process for Redox IIBP is jointly suggested by Design and Development and Chemical Development personnel, and is described in this document. This process is believed to be simple and easily operable. Acid is removed from the product solution adequately for the single peroxide strike coupling procedure. Batch size appears to be easily controllable.
Date: October 29, 1951
Creator: Tomlinson, R. E.
System: The UNT Digital Library
GENERAL RESEARCH REPORT FOR OCTOBER 2 TO DECEMBER 26, 1950. (Supporting Research Volume) (open access)

GENERAL RESEARCH REPORT FOR OCTOBER 2 TO DECEMBER 26, 1950. (Supporting Research Volume)

None
Date: January 29, 1951
Creator: unknown
System: The UNT Digital Library
ADDITIONAL PULSE COLUMN TESTS FOR URANIUM ORES RECOVERY PROCESS (open access)

ADDITIONAL PULSE COLUMN TESTS FOR URANIUM ORES RECOVERY PROCESS

None
Date: June 29, 1951
Creator: Jealous, A.C.
System: The UNT Digital Library
Filter capacity tests (open access)

Filter capacity tests

Increases in production rates in the 100 Areas have caused a demand for additional amounts of cooling water for process use. Consequently, continual efforts have been made to push the existing filter plants well beyond designed capacity. The latest and most successful effort was made at the 100-B filter plant during the spring of 1951. Tests of the 100-B Area indicate that the 100 Area filters can be operated safety at 3,400 GPM per unit, or 13.3% beyond the designed capacity, during the period of most difficult water treatment (February-June). By extrapolation of the data to the most favorable water treatment periods (August--January), it is indicated that net water available for production use is approximately 5% above 3400 GPM. It is recommended that no additional filter plant capacity be installed in existing areas until anticipated water loads exceed 3,400 GPM per filter basin unit. It is further recommended that an investigation be made of the feasibility of changing water flows to the piles on a seasonal basis to take advantage of the fact that the season requiring the greatest theoretical quantity of water (because of high raw water temperatures) is also the season during which it is easiest to produce …
Date: June 29, 1951
Creator: Conley, W. R.
System: The UNT Digital Library
Review of the feasibility of the air cycle nuclear reactor (open access)

Review of the feasibility of the air cycle nuclear reactor

None
Date: November 29, 1951
Creator: Lane, J. A.
System: The UNT Digital Library
New reactor area (open access)

New reactor area

This memorandum discusses discusses the design of a new reactor area in relation to the H pile.
Date: January 29, 1951
Creator: Gross, C. N.
System: The UNT Digital Library
Pile Technology Test Report: Flapper Nozzle Assembly (open access)

Pile Technology Test Report: Flapper Nozzle Assembly

The functional operation of the flapper nozzle was tested by charging slugs through it while water flow rates up to 48.4 gpm and inlet header pressures up to 400 psig. were maintained. Comparative damage to the slugs by the flapper nozzle and an H-type inlet nozzle was determined by charging slugs through the nozzles with a 105-D type air cylinder charging machine under conditions of no water flow or lubrication. The effect of the nozzle design on the inlet pressure fluctuations was determined while using 0.140, 0.200, and 0.285 inlet orifices as well as no orifice. The flapper nozzles operated satisfactorily for all conditions tested, without leakage from the flapper valve or the needle valve. However, the flapper valve became loosened on the shaft after several operations, and it is felt that the design should be changed to insure that it is rigidly fastened to the shaft at all times. Damage to the slugs by either the flapper nozzle or the H-type inlet nozzle was negligible. The ribs of the process tube caused the normal parallel, longitudinal scratches the length of the slugs. Maximum fluctuations of {+-} 5 psig were noted on the inlet pressure gauge reading, at compared with …
Date: December 29, 1951
Creator: Schilson, R. E.
System: The UNT Digital Library
Dissolve -- silver reactor temperature requirements (open access)

Dissolve -- silver reactor temperature requirements

None
Date: August 29, 1951
Creator: Evans, L. C.
System: The UNT Digital Library
Survey of required equipment charges for RMA and RMB lines, 234-5 Building, incurred by model changes (open access)

Survey of required equipment charges for RMA and RMB lines, 234-5 Building, incurred by model changes

None
Date: March 29, 1951
Creator: unknown
System: The UNT Digital Library
Constant chemical addition to reduction operation in the 234-5 Building (open access)

Constant chemical addition to reduction operation in the 234-5 Building

At the request of the ``S`` Division, a study has been made regarding the feasibility of simplifying operations by standardizing the amounts of chemical additions made at the reduction step as is the current practice in the purification operation. The investigation included a study of the following items, which are discussed under separate headings: (1) variation in feed; (2) maximum variation in booster ratios and per cent excess calcium using the method; and (3) chemicals handling and storage procedures. The process reduces plutonium fluoride to the metal.
Date: July 29, 1951
Creator: Quinn, F.J.
System: The UNT Digital Library
List of equipment changes required for the production of various model sizes on the RMA and RMB lines, 234-5 Building (open access)

List of equipment changes required for the production of various model sizes on the RMA and RMB lines, 234-5 Building

In order to change models on the RM Line, a number of equipment items must be either replaced or modified. Some items may not necessarily require replacement depending upon the severity of the change. The attached list of items will require replacement or modification before production can be shifted from the present model to any of the others previously produced at this plant. The equipment is part of the Remote Mechanical A and B lines of the Plutonium Finishing Plant.
Date: August 29, 1951
Creator: Beaulieu, O.F.
System: The UNT Digital Library